GKN St. Louis-Plant Issues

Auto Time

 

     Item                                                                                                   Action                                                                                     Resp/Due

  Clocking

Ø        Issues clocking on Weekends-Autotime                                    Contact Karl Gabor update Timekeeping System                      D.Loop/Feb 22

Requires   system reprogramming & update from IT               K. Gabor/June 30

Communication
 

Ø        Update people on company performance events, changes        Bi Monthly meeting with shop stewards                                   Wacker / Started Nov.07

Etc.

 

Ø       Be sensitive on delivering messages                                        Monthly meeting with Union officials

Weekly newsletter                                                                  Weih/Ongoing

                                                                                                Pulliam/March08

                                                                                                Smith/March08

All hands meetings BU                                                           Weih/June08

All hands meetings Site                                                           Smith/08

Daily Cell starts by team leaders                                           Weihl/Pulliam/Ongoing

 

Respect

Ø       Treat people with respect                                                     

Ø       Monitor Issues with supervisors & managers                        Providing Training all supervisors                                          Dorf, Wacker/ starts

Supervisors’                                                                                            w/Feb 25

 

Provide specialized team bldg. Training for new                    Dorf, Loop/April08

Supervisors

 

Ø       New supervisors do not know how to treat employees

 

Ø       With respect and motivate them                                             Training to be provided                                                          Dorf ,Loop/April08

 

 

Ø       Eliminate favoritism                                                                Mentoring program to be established                                     Weihl/Pulliam/

Wacker/March08

Communication
 

Ø       Involve people in improvement plans, example is Modig      Have participate in Modig relocation plans                           Bauer/Feb29

Relocation                                                                               relocation plans

 

                                                                                                Communicate Kaizens & employees involvement                 Koenemann/

                                                                                                Activities in improving the processes                                    VanStratten/

                                                                                                                                                                                                March08

                                                                                                Publish in BU updates, weekly newsletters/all

                                                                                                Hands meetings, etc.

 

                                                                                                Put Union Hall on distribution for                                         Wacker/March08

                                                                                                all plant communications

 

Training

 

Ø       Monitor new hire orientation for improvements                    Created training department-initial                                         Dorff/Jan08

Ø       Review timing of improvements                                             focus Composites

Ø       Issue with employees evaluating other employees                                Two weeks of classroom training

Before OJT starts                                                                   McAllister/Jan08

 

Ø        Include chemical handling in new hire orientation                  To be added to training program with                                    McAllister/March08

Ø       Publish a list of who has OV stamps & what they         Add to skills matrix on cell boards                                    Schuster/Mink/

are certifying                                                                                                                                                                         March

                                                                                                        Add to intranet web site                                                     B. Green/April 1508

Ø        Allow new employees time on a particular                      Based on evaluation Process-new                                    Shuster/Mink/Jan08

Job before moving them to another                                         Jan08                                                                                      

 

                                                                                                Adopt OJT Training from Alabama Site                                Schuster/Complete

                                                                                                                                                                                                Jan08

Safety

Ø       Snow Issues                                                                            Assign responsibility to monitor/fix issues                            Wolverton/Started

With parking lots and walkways on snow/ice days               Feb 18

Ø       Identify & Create aids to help lift heavy items                      Being investigated                                                                   Pierangli/March 15

Before someone gets hurt                                                      

 

 

 

Safety

Ø       Consistent policy on bringing people back on light duty       Ops Directors will accommodate as needed                           Schuster/Mink/

Ongoing

Ø       People crossing aisles due to running two or three                 New assignments for machinists being                                   Mink/March30

Machines                                                                                                established                                                             

Ø        Uneven floors in cryoblast area                                              Reviewing with facilities for improvement plan                     Pierson/Finocchiaro/

March08

Ø        Dirty bathrooms                                                                      Added three heads to Good will for spot                                   Wolverton/started

Cleanup & painting-short term                                                                Feb08

 

Long term-to be investigated                                                   Koclanes/March30

 

Ø        Water on floor in bathrooms in sheet metal                                             Plumbing issues with toilet                                                       Finocchiaro/Compl

Feb25

 

Ø        Fix dock door in Bldg one where it has been broke for some     Investigate best option with help of employees in area                            Clancy/April 15

Employees in area

 

Ø        Setup employees in Machining are being split up-causes           Investigates issue & solutions with help of setup employees     Mink/Davis/

Issues when moving material because it takes two to work                                                                                                        Giancarlo/March 15

Safely

Overtime
 

Ø        3rd shift doesn’t get overtime                                                   Overtime is proportionate to the number of employees                           Weihl/Compl

employees on each shift.  Will try to keep

shifts balanced with staffing.

 

Ø        Request to come in early on weekends so they can get                             No change to current position                                                  Wacker/Compl

Out early

 

Policies
 

Ø       Need process for emergency phone calls                        Policy in place – guards communicate to                         Compl

First responders on shift via radios and they

Get with team leads

 

                                                                                                        Communication of policy with phone

                                                                                                        Number to be communicated by team leads                    Wacker/March15

                                                                                                        And in newsletter and posted

 

Ø       Request to bring in personnel radios                               No change to current policy                                              Weihl/Pulliam/

Compl

 

Ø       Absenteeism policy-causes bad morale                           No change in current no-fault policy                                Weihl/Pulliam/

Compl

 

Ø       Scrap Policy-be consistent when applying policy         Change to policy to first offense                                       Wacker/Weihl/

Pulliam/Started

Feb 18

 

Ø       Buyers get wrong materials but they don’t get              Confidential matter with discipline                                    Weihl/Pulliam/

Written up                                                                                                                                                                             Compl

 

Ø       Reward for perfect attendance needed                             Investigating site wide program-will get                          Loop/April 15

Cross-functional input from employees

 

Work Orders/Work

Instructions/Materials/Equipment
 

Ø       Need accurate work orders/work instructions                                To be investigated on specific issues                              Bowman/TBD

 

 

Ø       Make sure we have proper equipment &                         To be investigated on specific issues                              Weihl/Pulliam/

Materials                                                                                                                                                                               March 15

 

Ø       Allow us to go home without pay if we don’t Employees to be reassigned wherever                             Shuster/Mink

have proper equipment or materials                                  possible                                                                                 Feb29

 

Ø       Air tools requested for a long time to deburr &              Order air tools for deburr employees                                Pulliam/Compl

supervisor will not order                                                                                                                                                     Feb 22

 

                                                                                                        Investigate/resolve other shortage issues                      Schuster/Mink

                                                                                                        throughout plants                                                                   March 15

 

Ø       Need proper measuring equipment to setup on HL3-            Order measuring equipment for H.L.                                      Dallas/Compl

Have to get maintenance to help each time.                                                                                                                            Feb. 25

                                                                                                Investigate/resolve other shortages throughout plant             Schuster/Mink/

                                                                                                                                                                                                March 15

 

Ø       Not a decent lathe in the building-need to review                   Fix or replace lathes & other needed tool                               Mink/Pulliam/

Status of equipment                                                                                room equipment                                                                      March 30

 

 

Work Orders/Work Instructions/

Materials/Equipment

 

Ø       Tool present crib is behind and we cannot get tools              Added two people to present crib                                          Mink/Feb 18

Present unless our machines go down-bad process                                                                                                                compl

 

                                                                                                Changing procedure for ordering tools                                    VanStratten/

                                                                                                                                                                                                April 30

 

Ø       Spares and stocking levels of tools in Bldg. 2 are                   All Min/Max at point of use cabinets to be                           Pierson/Bauer/

Causing downtime-need to look at and adjust                        reviewed and adjusted as needed                                            March 30